Monday, May 9, 2011
I have added the plans and elevations slide show to the right. This week the engineering for the roof will be completed. The applications for permits will be submitted next week. The material lists are being compiled. Upon getting the permit approvals the schedule of events are as follows: 1. stake out for the dig 2. dig and prepare footers with steel 3. concrete pour the footers 4. stake out for block work 5. place 2 courses of block 4. plumbing for all the drain lines 5. spreading stone, plastic, perimeter insulation 6. set grade pegs for concrete slab and finally pour and seal the slab. Then we will be ready to start framing!